New Pipeline Projects
 

Sabal Trail Transmission & Florida Southeast Connection

To ensure we have reliable access to the clean, affordable, U.S.-produced fuel necessary to meet the growing electricity needs of the state’s residents and businesses, FPL issued a request-for-proposals (RFP) in December 2012 for new natural gas transportation infrastructure into and within Florida beginning in 2017. After a fair, competitive evaluation process, FPL determined that the best, most economical solution is a combination of a natural gas pipeline and interconnection hub to be built by Sabal Trail Transmission, LLC, and a second natural gas pipeline to be built by Florida Southeast Connection, LLC.

  • Sabal Trail Transmission: Sabal Trail Transmission, a joint venture of Spectra Energy Corp. and NextEra Energy, Inc., will include approximately 465 miles of interstate natural gas pipeline that will originate in southwestern Alabama and transport natural gas to Georgia and Florida. It will terminate at a new Central Florida Hub south of Orlando, Fla., where it will interconnect with the two existing natural gas pipelines that currently serve central and southern Florida. The Sabal Trail pipeline will be capable of transporting more than 1 billion cubic feet per day of natural gas to serve local distribution companies, industrial users and natural gas-fired power generators in the Southeast.
  •  

  • Florida Southeast Connection: Florida Southeast Connection, LLC is a wholly owned subsidiary of NextEra Energy. To connect with FPL’s operations, Florida Southeast Connection will construct a separate, 126-mile pipeline from Sabal Trail’s Central Florida Hub to FPL’s Martin Clean Energy Center in Indiantown, Fla.

 

The two projects are expected to be completed and begin delivering natural gas to FPL’s system in May 2017. FPL will purchase approximately 400 million cubic feet per day beginning in 2017, and will increase to about 600 million cubic feet per day in 2020.

Project Timeline

December 2012: FPL issues RFP for new natural gas infrastructure.
July 2013: FPL selects two companies to build two pipeline systems.
Fall 2013: Sabal Trail and Florida Southeast Connection begin permitting process with the Federal Energy Regulatory Commission.
Spring 2016: Construction on the two pipeline systems is expected to begin.
May 2017: The two pipeline systems begin delivering natural gas into FPL’s system.