Tier Three (>100kW-2mW)

Close Window
Follow these steps to participate in the program:

Review FPL's Net Metering Guidelines to help you achieve a system that best suits your needs.


View and print the Tier Three Agreement: Tier Three (>100kW-2mW)

Complete the Agreement with your signature either witnessed or notarized.  The customer of record on the FPL account must execute this Agreement.


View and print the Application.

Complete the Application.


Submit the following to FPL:
  • Completed Application and Agreement
  • Documentation showing proof of insurance per the Agreement
  • An electrical one-line diagram, showing the electrical and physical location of the visual, manual load break disconnect switch, and specification sheets for the inverter and other installed equipment, such as PV panels
FPL will review your plans and inspect the FPL facilities that serve you to make sure the two systems are compatible.

FPL will send you a letter acknowledging receipt and review of the above documentation, and will also sign and return a copy of the executed Agreement.

FPL will then invoice you for the $1,000 Application fee. When you receive this invoice, please send FPL a check in that amount.


Once construction is complete, have your system inspected by the local Authority that has jurisdiction and submit a copy of the completed permit.. Submit a copy of the final permit showing the system approved and signed off.

FPL will change the meter within 30 days of receipt of all of the above-mentioned completed paperwork.


Do not begin parallel operation until your bidirectional meter is installed.

Prior to installation of the new meter the system should be turned on only for testing and inspection.

Paperwork may be submitted to FPL by:

E-mail - scan and e-mail to Netmetering@fpl.com

Mail - send to:

Manager of Transmission Services
FPL – Mail Code TSP/LFO
4200 West Flagler Street
Coral Gables, FL 33134

Phone: (305) 442-5199