Follow these steps to participate in the program:
View and print the Tier Three Agreement: Tier Three (>100kW-2mW) Complete the Agreement with your signature either witnessed or notarized. The customer of record on the FPL account must execute this Agreement. |
|
| View and print the Application. Complete the Application. |
|
Submit the following to FPL:
FPL will send you a letter acknowledging receipt and review of the above documentation, and will also sign and return a copy of the executed Agreement. FPL will then invoice you for the $1,000 Application fee. When you receive this invoice, please send FPL a check in that amount. |
|
| Once construction is complete, have your system inspected by the local Authority that has jurisdiction and submit a copy of the completed permit.. Submit a copy of the final permit showing the system approved and signed off. FPL will change the meter within 30 days of receipt of all of the above-mentioned completed paperwork. |
|
| Do not begin parallel operation until your bidirectional meter is installed. Prior to installation of the new meter the system should be turned on only for testing and inspection. |
Paperwork may be submitted to FPL by:
E-mail - scan and e-mail to Netmetering@fpl.com
Mail - send to:
Manager of Transmission Services
FPL – Mail Code TSP/LFO
4200 West Flagler Street
Coral Gables, FL 33134