Tier Two (>10kW-100kW)
Follow these steps to participate in the program:
|
Step |
Action |
|
1 |
Review FPL's Net Metering Guidelines to help you achieve a system that best suits your needs. |
|
|
2 |
View and print the Tier Two Agreement: Tier Two (>10kW-100kW)
Complete the Agreement with your signature either witnessed or notarized. The customer of record on the FPL account must execute this Agreement. |
|
| 3 |
View and print the Application.
Complete the Application. |
|
|
4 |
Submit the following to FPL:
FPL will review your plans and inspect the FPL facilities that serve you to make sure the two systems are compatible.
FPL will send you a letter acknowledging receipt and review of the above documentation, and will also sign and return a copy of the executed Agreement.
FPL will then invoice you for the $400 Application fee. When you receive this invoice, please send FPL a check in that amount. |
|
|
5 |
Once construction is complete, have your system inspected by the local Authority that has jurisdiction. Send FPL a copy of the final permit showing the system approved and signed off.
FPL will change the meter within 30 days of receipt of all the above-mentioned completed paperwork and payment. |
|
|
6 |
Do not begin parallel operation until your bidirectional meter is installed.
Prior to installation of the new meter the system should be operated only for testing and inspection. |
|
|
Paperwork may be submitted to FPL by:
E-mail - scan and e-mail to Netmetering@fpl.com
Mail - send to:
Net Metering FPL-Mail Code PMD-GO 9250 W. Flagler St. Miami, FL 33174
FAX - 305-552-2487 |
|
|
|
|
|
|
|
|